Discussion Forum : Production And Industrial
Question - Data for four jobs that need to be processed on a single machine are given below.Job                                     P  Q   R    SProcessing time (days)  12 9   21 10Due date (days)              20 40 30 19All the four jobs are available at time zero. If the jobs are scheduled using the Earliest Due Date (EDD) algorithm, then the job with maximum tardiness is
Options:
A .  P
B .  Q
C .  R
D .  S
Answer: Option C


-NA-