Question - Which one of the following is NOT a decision taken during the aggregate production planning stage?
Options:
A .  Scheduling of machines
B .  Amount of labour to be committed
C .  Rate at which production should happen
D .  Inventory to be carried forward
Answer: Option A


-NA-