Discussion Forum : Flexible Budget And Management Control
Question - In the budget hierarchy, the material handling cost is
Options:
A .  fixed manufacturing cost
B .  batch level cost
C .  per unit cost
D .  factory overall cost
Answer: Option B
Answer: (b).batch level cost