Question -
Green Energy Corridor Project (GEC) is related to:
Options:
A .  developing Industrial corridor based on renewable energy.
B .  facilitate the flow of renewable energy into the National grid.
C .  establishment of Bio-gass plants in rural area.
D .  establishment of solar-energy plants in rural area.
Answer: Option B Answer: (b)Union government has planned to roll out a 43000 crore rupees Green Energy Corridor Project to facilitate the flow of renewable energy into the national grid.