Question - In CPM, the cost slope is determined by
Options:
A .  Crash cost/Normal Cost
B .  (Crash Cost - Normal cost)/ (Normal time - Crash time)
C .  Normal Cost/Crash cost
D .  (Normal cost - Crash cost)/ (Normal time - Crash time)
Answer: Option B