Discussion Forum : Industrial Engineering And Production Management
Question - Actual performance of a task is called
Options:
A .  An event
B .  An activity
C .  A duration
D .  None of these
Answer: Option B

Submit Your Solution Below and Earn Points !
Next Question
Submit Your Solution hear:

Your email address will not be published. Required fields are marked *