Sap Qm(Engineering > Computer Science And Engineering ) Questions and Answers

Question 1. Factual approach to decision making is a
  1.    Quality products
  2.    Quality principle
  3.    Quality procedure
  4.    None
Explanation:-
Answer: Option B. -> Quality principle





Question 2. Which of the following Transaction code is used for scheduling UD for Production lot?
  1.    QA39
  2.    QA40
  3.    QA41
  4.    QA42
Explanation:-
Answer: Option C. -> QA41





Question 3. Which type of control charts are based on the specified tolerance and control the share of scrap in the process?
  1.    Acceptance charts
  2.    Shewhart charts
  3.    mean-value chart
  4.    Statistical Graphics
Explanation:-
Answer: Option A. -> Acceptance charts





Question 4. Which finger is used to strike the slash?
  1.    Right middle
  2.    J-Finger
  3.    Right Pinky
  4.    K-finger
Explanation:-
Answer: Option C. -> Right Pinky





Question 5. In manufacturing with QM, you can confirm the inspection results to QM in two ways- can call up results recording in QM directly from the process instruction (PI) sheet or can copy summarized inspection results from process messages. The above is true for
  1.    Only Discrete Manufacturing
  2.    Only Process Manufacturing
  3.    Either Discrete or Process Manufacturing
  4.    Neither Discrete nor Process Manufacturing
Explanation:-
Answer: Option B. -> Only Process Manufacturing





Question 6. In Audit Management, the information relevant to the data elements becomes available if the
  1.    Audit object can be defined by Data elements from repository resulting from the Information Record maintained
  2.    Audit object can be defined by Data elements from a repository such as a combination of supplier and material
  3.    Audit objects are cleared through the Quality Management processes
  4.    Pre-Audit approvals are in place
Explanation:-
Answer: Option B. -> Audit object can be defined by Data elements from a repository such as a combination of supplier and material





Question 7. Control of documents is a
  1.    Documentation
  2.    Quality procedure
  3.    Data Procedure
  4.    None
Explanation:-
Answer: Option B. -> Quality procedure





Question 8. Quality Management data is primarily maintained at the
  1.    Cost Centre level
  2.    Plant level
  3.    Company code level
  4.    Sales Organization level
Explanation:-
Answer: Option B. -> Plant level





Question 9. Which of the following is not a control parameter that can be set on the material master for Quality Management.
  1.    MRP Type
  2.    Inspection Type
  3.    Sample Determination
  4.    Requirements for the vendor's QM system
Explanation:-
Answer: Option A. -> MRP Type





Question 10. Which of the following Transaction code is used to create an Inspection Plan?
  1.    QS21
  2.    QS31
  3.    QDV1
  4.    QP01
Explanation:-
Answer: Option D. -> QP01