Question 1. After MRP run, which of the following gets created in Planning?
  1.    Production Order & Planned Order
  2.    Purchase Order
  3.    None of the above
  4.    Scheduling Lines
Explanation:-
Answer: Option A. -> Production Order & Planned Order





Question 2. What are the reports generated in product cost controlling information system?
  1.    Product cost planning
  2.    Cost object controlling with the subcomponents
  3.    Actual Costing / Material Ledger
  4.    All of these
Explanation:-
Answer: Option D. -> All of these





Question 3. In Material Requirement Planning
  1.    Material availability is ensured
  2.    If shortage exists the corresponding elements are planned
  3.    Stock transfers are also possible
  4.    The availability of the components is ensured via dependent requirements
Explanation:-
Answer: Option D. -> The availability of the components is ensured via dependent requirements





Question 4. Planning can create the following after MRP run
  1.    Planned Orders
  2.    Production Orders
  3.    Purchase Orders
  4.    Schedule Lines
Explanation:-
Answer: Option A. -> Planned Orders





Question 5. Settlement in product cost controller is based on
  1.    Period-oriented
  2.    Costs of the product cost controller
  3.    Order settlement
  4.    No settlement rule
Explanation:-
Answer: Option A. -> Period-oriented





Question 6. A purchasing group is a sub-set of a purchasing organization?
  1.    Yes
  2.    No
  3.    All of these
  4.    None
Explanation:-
Answer: Option A. -> Yes





Question 7. BOMs are always created as
  1.    Single Level
  2.    Multi-Level
  3.    Components
  4.    Along with routings
Explanation:-
Answer: Option A. -> Single Level





Question 8. Where can you define the valid receivers for production order costs?
  1.    In the valuation variant
  2.    In the production scheduling profile
  3.    In the settlement profile
  4.    In the costing variant
Explanation:-
Answer: Option B. -> In the production scheduling profile





Question 9. What are the production process in SAP?
  1.    Discrete Manufacturing
  2.    Repetitive Manufacturing
  3.    Production- Process Industries
  4.    All of these
Explanation:-
Answer: Option D. -> All of these





Question 10. In Material Requirement Planning
  1.    Material availability is ensured
  2.    If a shortage exists the corresponding elements are planned
  3.    Stock transfers are also possible
  4.    The availability of the components is ensured via dependent requirements
Explanation:-
Answer: Option D. -> The availability of the components is ensured via dependent requirements