Microsoft Project(Engineering > Computer Science And Engineering ) Questions and Answers

Question 1. Out of the following constraints, select the one which doesn't require start or finish date to be added in order to schedule a task in MS Project.
  1.    SNET
  2.    FNLT
  3.    ALAP
  4.    MFO
Explanation:-
Answer: Option C. -> ALAP





Question 2. What are the types of constraint available in MS project?
  1.    As soon as possible
  2.    As late as possible
  3.    Both A and B
  4.    None of these
Explanation:-
Answer: Option D. -> None of these





Question 3. What are the new features available in MS project?
  1.    Improved reporting tools
  2.    Office 365 Integration
  3.    New Project Templates
  4.    All the above
Explanation:-
Answer: Option D. -> All the above





Question 4. How to set a deadline in MS project?
  1.    Double-click a task -> it will open a task information dialog box
  2.    Now, click on the advanced tab
  3.    Then click on the arrow in the deadline field to show the calendar and then choose a date
  4.    All of the above
Explanation:-
Answer: Option D. -> All of the above





Question 5. What are the categories of tasks used in MS project?
  1.    Summary tasks
  2.    Subtasks
  3.    Recurring tasks
  4.    All of these
Explanation:-
Answer: Option D. -> All of these





Question 6. What are the different types of contour you use in MS project?
  1.    Flat
  2.    Back-loaded
  3.    Front-loaded
  4.    All of the above
Explanation:-
Answer: Option D. -> All of the above





Question 7. What are the types of task links in MS project?
  1.    Finish to start link
  2.    Start to start link
  3.    Finish to finish link
  4.    All of the above
Explanation:-
Answer: Option D. -> All of the above





Question 8. How to set work time exception in Project?
  1.    Select the project and change the working time
  2.    On the calendar choose the day you want to change
  3.    Click the exception tab to display it, it will show a column with the name cell in a blank row, type a name for the exception and press enter
  4.    All of these
Explanation:-
Answer: Option D. -> All of these





Question 9. You would like to see a list of all the resources and the tasks that they are assigned to. What view best displays this information?
  1.    Resource Sheet
  2.    Task Usage
  3.    Gantt Chart
  4.    Resource Usage
Explanation:-
Answer: Option C. -> Gantt Chart





Question 10. A(n) __________ determines how tasks and resources assigned to these tasks are scheduled.
  1.    Schedule
  2.    Exception plan
  3.    Calendar
  4.    Resource pool
Explanation:-
Answer: Option A. -> Schedule