Microsoft Project(Engineering > Computer Science And Engineering ) Questions and Answers
Question 1. Out of the following constraints, select the one which doesn't require start or finish date to be added in order to schedule a task in MS Project.
SNET
FNLT
ALAP
MFO
Explanation:-
Answer: Option C. -> ALAP
Question 2. What are the types of constraint available in MS project?
As soon as possible
As late as possible
Both A and B
None of these
Explanation:-
Answer: Option D. -> None of these
Question 3. What are the new features available in MS project?
Improved reporting tools
Office 365 Integration
New Project Templates
All the above
Explanation:-
Answer: Option D. -> All the above
Question 4. How to set a deadline in MS project?
Double-click a task -> it will open a task information dialog box
Now, click on the advanced tab
Then click on the arrow in the deadline field to show the calendar and then choose a date
All of the above
Explanation:-
Answer: Option D. -> All of the above
Question 5. What are the categories of tasks used in MS project?
Summary tasks
Subtasks
Recurring tasks
All of these
Explanation:-
Answer: Option D. -> All of these
Question 6. What are the different types of contour you use in MS project?
Flat
Back-loaded
Front-loaded
All of the above
Explanation:-
Answer: Option D. -> All of the above
Question 7. What are the types of task links in MS project?
Finish to start link
Start to start link
Finish to finish link
All of the above
Explanation:-
Answer: Option D. -> All of the above
Question 8. How to set work time exception in Project?
Select the project and change the working time
On the calendar choose the day you want to change
Click the exception tab to display it, it will show a column with the name cell in a blank row, type a name for the exception and press enter
All of these
Explanation:-
Answer: Option D. -> All of these
Question 9. You would like to see a list of all the resources and the tasks that they are assigned to. What view best displays this information?
Resource Sheet
Task Usage
Gantt Chart
Resource Usage
Explanation:-
Answer: Option C. -> Gantt Chart
Question 10. A(n) __________ determines how tasks and resources assigned to these tasks are scheduled.