Question 1. The manner in which the process of risk management is conducted depends on
  1.    Management impact
  2.    Technological impact
  3.    Environment impact
  4.    Conflicts
Explanation:-
Answer: Option C. -> Environment impact
Answer: (c).Environment impact

Question 2. Monitoring residual risks and identification of new risks is done at
  1.    Qualitative Risk Analysis
  2.    Risk monitoring and controlling
  3.    Quantitative Risk Analysis
  4.    Risk Identification
Explanation:-
Answer: Option B. -> Risk monitoring and controlling
Answer: (b).Risk monitoring and controlling

Question 3. A description of a task that defines all the work required to accomplish it, including inputs and desired outputs, is known as
  1.    Work statement
  2.    Problem statement
  3.    Work Definition
  4.    Problem definition
Explanation:-
Answer: Option A. -> Work statement
Answer: (a).Work statement

Question 4. A way of life for PMs and their projects, is
  1.    Certainty
  2.    Success ration
  3.    Uncertainty
  4.    Failure ratio
Explanation:-
Answer: Option C. -> Uncertainty
Answer: (c).Uncertainty

Question 5. In matric approach, the project is the point of emphasis, responsibility of managing the project is on
  1.    One Individual
  2.    Combinations of 2
  3.    Multiple Groups
  4.    One department
Explanation:-
Answer: Option A. -> One Individual
Answer: (a).One Individual

Question 6. To ensure against the memory risk, the risk management system should maintain an up-to-date
  1.    Data Book
  2.    Data bank
  3.    Data box
  4.    Data block
Explanation:-
Answer: Option B. -> Data bank
Answer: (b).Data bank

Question 7. Housing the project in a functional organization is simply too
  1.    Expensive
  2.    Cheap
  3.    Constraining
  4.    Easy installed
Explanation:-
Answer: Option C. -> Constraining
Answer: (c).Constraining

Question 8. The first sub process in the risk management process is
  1.    Risk Identification
  2.    Risk Response
  3.    Risk Management Planning
  4.    Risk monitoring and controlling
Explanation:-
Answer: Option C. -> Risk Management Planning
Answer: (c).Risk Management Planning

Question 9. The impetus for the matrix organization was the fact that firms operating in high technology areas had to integrate several
  1.    Functional Specialties
  2.    Managerial Specialties
  3.    Technical Specialties
  4.    Departmental Specialties
Explanation:-
Answer: Option A. -> Functional Specialties
Answer: (a).Functional Specialties

Question 10. Everything a risk management group does for any project should be retained in the risk
  1.    Planning
  2.    Analysis
  3.    Response
  4.    Database
Explanation:-
Answer: Option D. -> Database
Answer: (d).Database